
PROJECT OVERVIEW
Project Name: SVE/AS System Installation
Location: Riverside, CA
Job Type: Remediation System Installation
DESCRIPTION
Installing a 36-well Soil Vapor Extraction (SVE) remediation 12-well Air Sparge (AS) System to optimize the clean-up of our client’s high-profile project. This site required more than a standard remediation system installation – incorporating additional trenching, building rehabilitation, tank and pipe installations, crash barriers, parking lot resurfacing, and the excavation of VOC contaminated soils into the original scope.
MAIN TASKS
- SVE/AS systems installation
- Significant lengths of trenching and saw-cutting – through 12” thick, reinforced concrete
- Installation of 5,000ft of welded HDPE and 10,000ft of 2" to 12” diameter PVC conveyance lines
- Rehabilitation of a 60’ x 60’ x 40’ building to house the equipment including the installation of steel piping (carbon, stainless, and galvanized), all mechanical elements, and a PID room
- Equipment installation, including (2) 10,000lb carbon tanks, knock out pots, compressors, and receivers
- Generator refurbishment and relocation
- Mechanical and electrical work, including 2000' fiber optic runs and PLC system installation
- 30,000 square feet of asphalt paving and additional concrete forming / pouring
- Excavation and disposal of 1,000+ cu yds of contaminated soil
CHALLENGES
Cutting Through Reinforced Concrete – Initially, one of the biggest challenges was saw-cutting and the subsequent removal of a large quantity of 18” thick, heavily reinforced concrete. Special attention was given to safety as a result of heavy rebar. Disposal of the concrete required extra effort to separate this rebar adequately from concrete.
Undocumented Utility Lines – While trenching and saw-cutting, E&E discovered multiple undocumented underground lines and utilities. E&E’s team was subsequently asked to perform exploratory excavations in various locations – resulting in the discovery and removal/capping of 30 lines. E&E’s highly skilled equipment operators and spotters actually found and exposed all 30 lines without a single break!
Unexpected VOCs – During excavation, E&E Excavation and Spotter crews detected discolored soils and odors. This discovery ended up requiring further excavation, isolation and removal of over 1,000 tons of highly contaminated VOC soils. E&E managed the safe disposal of the solis and the subsequent import, backfilling and compaction of certified cleanfill.
Traffic Controls – This project was located in a high on-site traffic area, which required strict traffic control and sitewide notifications to ensure the safety of all staff and the surrounding community.
INTERESTING POINTS
The success of this high-profile installation – and our team’s ability to safely and efficiently implement solutions to a plethora of unexpected circumstances – resulted in E&E being awarded the ongoing operations & maintenance contract for this system. This project also initiated the subsequent award of multiple high visibility and high-value construction and remediation projects for the corporate client.




